01

Decide which deliveries you have grounds to stop

A defective shipment may justify rejecting or avoiding that instalment, but usually does not answer what to do about later deliveries. The key questions are whether the defect is serious enough for the remedy you want, what it shows about the remaining shipments, and whether the batches can serve their intended purpose separately. Suspending your own performance is temporary and has different conditions from ending contractual obligations.

Get the signed supply terms, purchase orders, delivery schedule and payment allocation before sending a cancellation. One supply contract with scheduled lots is different from several standalone purchase orders. A common price, one supplier or different PO numbers do not settle that issue. Check what the parties actually committed to, not just how invoices were issued.

02

Identify the legal test before writing the notice

The CISG commonly applies under Article 1(1)(a) where the relevant places of business are in different Contracting States and the goods sale is within its scope. Review any exclusion or variation under Article 6. Mainland China’s Article 95 reservation requires a forum-specific check before relying on Article 1(1)(b). This guide does not cover Hong Kong or Macao. A choice of Chinese law is not by itself a reliable shorthand for opting out; examine the wording and scope under the treaty and, in Chinese court, Articles 2–3 of the SPC interpretation on international treaties and usages.

Where mainland domestic law instead governs this issue, Civil Code Article 633 allows rescission of an affected instalment if failure to deliver conforming goods defeats its contractual purpose. If the breach prevents the purpose of subsequent deliveries, the buyer may rescind that and subsequent instalments. If deliveries are interdependent, rescission of one may extend to delivered and undelivered instalments. Do not replace those tests with the Convention’s future fundamental breach standard.

03

Match the remedy to what the evidence shows

Under CISG Article 25, fundamental breach turns on substantial deprivation of what the party was entitled to expect under the contract, subject to the foreseeability exception. A minor fixable marking problem and a failed critical function do not warrant the same decision. Run these four checks:

  • Deal with one instalment: use Article 73(1) only if the breach is fundamental as to that instalment. Otherwise assess repair, price reduction or damages where their conditions are met, and account for the seller’s right to cure (Articles 46, 48, 50 and 74).
  • Suspend your own performance: Article 71 applies when it becomes apparent after contracting that the other party will not perform a substantial part of its obligations for the reasons stated in the article. Notify the other party immediately and resume if it provides adequate assurance. It is not a general licence to stop paying every invoice.
  • Avoid future instalments: Article 73(2) requires a failure concerning an instalment that gives good grounds to conclude that a fundamental breach will occur in future instalments. An uncontained defect on the same line, failed retests, or evidence that correction cannot be completed in time can matter. Give the declaration within a reasonable time; document why a credible cure does or does not address the risk.
  • Extend avoidance to linked deliveries: Article 73(3) requires the buyer to declare avoidance of linked past or future deliveries at the same time, and show that because of interdependence they cannot be used for the purpose contemplated at contracting. Products from the same factory are not necessarily interdependent.

International contract disputes

04

Calendar inspection, notice and filing separately

Inspect each shipment as promptly as required in the circumstances. Under Articles 38–39, give a specific non-conformity notice within a reasonable time after actual or constructive discovery. Article 39 ordinarily also includes a two-year long-stop from actual handover, subject to inconsistent contractual guarantee periods; Article 40 limits reliance on the notice rules for defects the seller knew or could not have been unaware of and did not disclose. A defect report is not a declaration of avoidance. Article 26 requires notice to the other party.

If the mainland Civil Code applies, check inspection and notification terms against Articles 620–622, the separate time for exercise of rescission rights under Article 564, and delivery of the notice under Article 565. Where mainland limitation law governs an international goods sale, Article 594 provides a four-year period for bringing litigation or arbitration. Do not use that period as a deadline for inspection, suspension or cancellation notices. A shipment about to depart or a payment falling due may require immediate advice.

05

Build one ledger that separates the lots and the losses

For each lot, record the binding specification, quantity, delivery or shipping status, test result and discovery date, notice and delivery evidence, proposed cure, link to later batches, and what you have paid or are still being asked to pay. Preserve sealed retain samples where practical, original test data, lot labels, acceptance records and storage logs. Test the seller’s likely explanations separately: late notice, changed specifications, transit or storage damage, an isolated lot or a workable cure.

Before returning, disposing of or replacing goods, check lawful handling and recovery options. CISG Articles 81–82 address restitution and limits and exceptions where goods cannot be returned substantially in their original condition. Articles 74–77 address damages and mitigation; Article 75’s cover-price calculation requires a reasonable substitute purchase within a reasonable time after avoidance. If mainland domestic law applies, check Civil Code Articles 566, 584 and 591. Reconcile payments, credits, usable quantities and recoverable net loss without double counting. Confirm formal notice, dispute forum, the supplier entity and available assets before moving from negotiation to a claim; a favourable order is not cash collected.

Conclusion

If the next shipment, payment or notice deadline is close, address that first. This is general legal information, not advice on an individual sale, and it does not extend any deadline.